roadwork and construction workers

Updates to Euclid Avenue roadwork schedule

Roadwork on Euclid Avenue at the intersection of Adelbert Road will continue next week (Dec. 4–8).

The contractor will pour concrete Monday, Dec. 4, and Tuesday, Dec. 5, from 9 a.m. to 2:30 p.m.; these hours have been selected to avoid rush hour.

During the rest of the week, work hours are anticipated to be:

  • Wednesday, Dec. 6: 7 p.m. to 6 a.m.
  • Thursday, Dec. 7: 10:30 p.m. to 6 a.m.
  • Friday, Dec. 8: 10:30 p.m. to 6 a.m.

Work is expected to be completed Dec. 11.

Get more University Circle traffic updates at ugointhecircle.com/alerts.