Starting Wednesday, Nov. 13, work will begin on the Case Western Reserve Binary Walkway art, including excavation, concrete, and paver installation.
Concrete slabs are scheduled to be poured the week of Nov. 18, with paver installation expected to conclude in two weeks, by early December. CWRU letters will be installed in late January, while lawn repairs will follow in the spring after the winter work pause.